Title of the project
Reconstruction of Aeroflotska st.
Brief description (including physical parameters)
Length – 600 m.
shifting of power cable – 3270 m.
laying of asphalt concrete covering – 6672 m2.
laying of pavement – 1724 m2.
reconstruction of contact network of a trolley bus – 600 m.
Approximate cost (in national currency without VAT)
Aproximate cost of the project is 5729,0 UAH mln.
Stage of project preparation (projecting, feasibility study, environmental impact assessment, plan approval, the allotment of a land plot, tender procedures)
|
Approval stage (preparing) |
Date |
Stage (accepted/ in process/ planned) |
|
Project |
December 2008y. |
worked out |
Approved financial plan and status of confirmation of the financial capacity
Potential borrower of Euro loans, sources of repayment
Necessary technical assistance for project preparation
|