1. The name of the project |
|
Construction of the right-bank runway to Pivdenniy bridge over the Dnipro river, 2nd turn, from Milman str. - to Airportivska str. |
2. Brief description (including physical figures) |
|
Construction length - 2,7km |
|
Road category -IB |
|
Width of the traffic lane - 3,75 m |
|
Number of traffic lanes - 4 |
|
Width of the road - 2x7,5m |
|
The width of land lane: |
|
- within the city -26,5 m |
|
- outside the city - 27,5 m |
|
Width of the dividing strip: |
|
- within the city -2,5 м |
|
- outside the city — 5м |
|
Width of the sidewalk: |
|
- within the city -3,75 м |
|
- outside the city - 3,75 м |
|
Width of the supporting strip by the sideline - 0,75 м |
|
Width of the supporting strip on the dividing strip - 1 м |
|
Type of cover-capital |
|
Estimated rate - 100 km/hour |
|
Construction term - 13 months |
|
Demolition of private buildings - 3 pcs. |
|
Coefficient of motorway length - 1, 02 |
|
Volumes of land works - 324,1 thnd. m3 |
3. Approximate cost (local currency, without VAT) |
|
94,283mln. UAH |
4. Stage of project preparation (projecting, TEB, environment influence figure, approval of the plan , land allotment, bid procedures) |
|
Stage of approval (preparation) |
Date |
Stage (approved / in process / planned) |
|
Preparation of esteem papers |
August - September 2008 |
Is being approved by «DOS «ukrderzginvestexpertise» |
5. Approved financial plan and the stage of receipt of financial feasibility |
6. Potential credit borrower, source of credit repayment |
7. Necessary technical assistance for project preparation |
|
- Project works |
|
- Purchase assistance |
|
- Control of construction works' fulfillment |
|
- Contract management |
|
- Financial audit |
|
- Management support |
|
- Preparation of project estimates |