Construction of main line motorway from Kaidatskiy Shliakh str. to Kyiv-Lugansk-Izvaryne motorway
1. The name of the project

Construction of main line motorway from Kaidatskiy Shliakh str. to Kyiv - Lugansk - Izvaryne motorway

2. Brief description (including physical figures)

Length of road - 6,047 km

Construction length - 5,181 km

Road category - main line motorway of continuous movement

Rated speed - 90 km/h

Width of the traffic lane — 3,75 m

Number of traffic lanes - 2 in each direction

Width of the central demarcation strip - 3,0 m

Width of the safety lane -2x0,5m

Width of road bed- 26 m

Width of sidewalk - 2x3,00 m

Width of green zone - 2x0,5 m

Artificial facilities:

  • flyover through industrial area - 1/1069,74 pcs/m
  • railroad overpass over the railway tracks - 1/155,6

Construction term (standard) — 68 months

3. Approximate cost (local currency, without VAT)

UAH 837,640mln.

4. Stage of project preparation (projecting, TEB, environment influence figure, approval of the plan , land allotment, bid procedures)

Stage of approval (preparation)

Date

Stage (approved / in process / planned)

Stage «Project»

16.05.08

Developed, approved by "Ukrderzginvestexperiza" №98/197

5. Approved financial plan and the stage of receipt of financial feasibility
6. Potential credit borrower, source of credit repayment
7. Necessary technical assistance for project preparation
  • Project works
  • Purchase assistance
  • Control of construction works'fulfillment
  • Contract management
  • Financial audit
  • Management support
  • Preparation of project estimates



 
 